Introduction
Concrete is ordered in cubic metres and paid for whether it is used or not. The calculation is simple; the judgement is in the allowance for waste, spillage and uneven subgrade.
A short pour is far more expensive than a small over-order, which is why a 5 to 10 % allowance is standard on slab and footing work.
Volume from geometry
Slabs and rectangles are length × width × depth, all in metres. Footings and trenches are usually measured as a cross-section multiplied by length.
Convert millimetre dimensions before multiplying: a 125 mm slab is 0.125 m. Mixing units here is the most common source of a ten-fold error.
Allowances
Add 5 % for a formed slab on a prepared base, and up to 10 % where the subgrade is uneven, the excavation is irregular, or the pour is small and losses are proportionally larger.
For strip footings in trenches, over-excavation is normal — a trench that is 50 mm wide over its length can add several percent to the volume.
Mix quantities
Ready-mixed concrete is specified by strength grade and supplied to AS 1379, with slump and maximum aggregate size nominated for the placement. Site-batched concrete uses a nominated cement content per cubic metre.
Cement content of about 300 to 350 kg/m³ is typical for general structural work, but the mix design, not a rule of thumb, sets the actual value. Always use the supplier’s mix design rather than a remembered ratio.
[F]Technical formulas
Slab volume
V = L × W × D
All dimensions in metres.
Order quantity
V(order) = V × (1 + allowance)
Allowance typically 0.05 to 0.10.
Cement mass
m(cement) = V × cement content
Cement content in kg/m³.
[V]Explanation of variables
| Symbol | Meaning | Unit |
|---|---|---|
| V | Concrete volume | m³ |
| L | Length | m |
| W | Width | m |
| D | Depth or thickness | m |
[E]Worked example
A 6 m × 4 m slab at 125 mm
- 01V = 6.0 × 4.0 × 0.125 = 3.00 m³.
- 02Add 5 % for a formed slab on a prepared base: 3.15 m³.
- 03Order 3.2 m³ — suppliers work in increments, so round up to the next step.
- 04At 320 kg/m³ cement content, the pour consumes about 1 008 kg of cement.
Result
Three cubic metres by geometry, 3.2 m³ on the docket. The extra 0.2 m³ costs far less than a part-finished slab.
[A]Practical applications
- Ordering concrete for a slab, footing or pier.
- Estimating cement and aggregate for site batching.
- Checking a contractor’s claim for a pour volume.
- Estimating the mass of a finished slab for structural or lifting checks.
[!]Common mistakes
- Mixing millimetres and metres in the same multiplication.
- Forgetting to allow for over-excavation in trench footings.
- Ordering exactly the calculated volume for a slab pour.
- Using a remembered cement ratio instead of the supplied mix design.
[S]References and sources
- AS 3600 – Concrete structuresStructural design requirements for concrete.
- AS 1379 – Specification and supply of concreteHow concrete is specified and supplied.
- AS 2870 – Residential slabs and footingsSlab and footing requirements for residential work.
Standards are cited by designation and title only — no clause text is reproduced. Purchase current editions from Standards Australia, and confirm the edition that applies to your project.
PROJECT INTELLIGENCE
Know the project before the tender
A calculation only answers the question you were asked. Project Atlas tracks industrial projects, tenders and procurement activity so the work behind the number is visible.