Concrete Volume, Wastage and Mix Quantities

From dimensions to cubic metres to bags of cement, with the waste allowance and the ordering rules that keep a pour from finishing short.

5 MIN READ3 SECTIONS

Introduction

Concrete is ordered in cubic metres and paid for whether it is used or not. The calculation is simple; the judgement is in the allowance for waste, spillage and uneven subgrade.

A short pour is far more expensive than a small over-order, which is why a 5 to 10 % allowance is standard on slab and footing work.

Volume from geometry

Slabs and rectangles are length × width × depth, all in metres. Footings and trenches are usually measured as a cross-section multiplied by length.

Convert millimetre dimensions before multiplying: a 125 mm slab is 0.125 m. Mixing units here is the most common source of a ten-fold error.

Allowances

Add 5 % for a formed slab on a prepared base, and up to 10 % where the subgrade is uneven, the excavation is irregular, or the pour is small and losses are proportionally larger.

For strip footings in trenches, over-excavation is normal — a trench that is 50 mm wide over its length can add several percent to the volume.

Mix quantities

Ready-mixed concrete is specified by strength grade and supplied to AS 1379, with slump and maximum aggregate size nominated for the placement. Site-batched concrete uses a nominated cement content per cubic metre.

Cement content of about 300 to 350 kg/m³ is typical for general structural work, but the mix design, not a rule of thumb, sets the actual value. Always use the supplier’s mix design rather than a remembered ratio.

[F]Technical formulas

Slab volume

V = L × W × D

All dimensions in metres.

Order quantity

V(order) = V × (1 + allowance)

Allowance typically 0.05 to 0.10.

Cement mass

m(cement) = V × cement content

Cement content in kg/m³.

[V]Explanation of variables

SymbolMeaningUnit
VConcrete volumem³
LLengthm
WWidthm
DDepth or thicknessm

[E]Worked example

A 6 m × 4 m slab at 125 mm

  1. 01V = 6.0 × 4.0 × 0.125 = 3.00 m³.
  2. 02Add 5 % for a formed slab on a prepared base: 3.15 m³.
  3. 03Order 3.2 m³ — suppliers work in increments, so round up to the next step.
  4. 04At 320 kg/m³ cement content, the pour consumes about 1 008 kg of cement.

Result

Three cubic metres by geometry, 3.2 m³ on the docket. The extra 0.2 m³ costs far less than a part-finished slab.

[A]Practical applications

  • Ordering concrete for a slab, footing or pier.
  • Estimating cement and aggregate for site batching.
  • Checking a contractor’s claim for a pour volume.
  • Estimating the mass of a finished slab for structural or lifting checks.

[!]Common mistakes

  • Mixing millimetres and metres in the same multiplication.
  • Forgetting to allow for over-excavation in trench footings.
  • Ordering exactly the calculated volume for a slab pour.
  • Using a remembered cement ratio instead of the supplied mix design.

[S]References and sources

  • AS 3600 – Concrete structuresStructural design requirements for concrete.
  • AS 1379 – Specification and supply of concreteHow concrete is specified and supplied.
  • AS 2870 – Residential slabs and footingsSlab and footing requirements for residential work.

Standards are cited by designation and title only — no clause text is reproduced. Purchase current editions from Standards Australia, and confirm the edition that applies to your project.