[CIVIL ENGINEERING]

Cut, Fill, Swell and Compaction Factors

Why a cubic metre in the ground is not a cubic metre in the truck, and how bulking, shrinkage and density control the earthworks balance.

5 MIN READ3 SECTIONS

Introduction

Soil changes volume at every stage of the process: in the ground it is bank volume, excavated it bulks and becomes loose volume, compacted it shrinks back to something denser than it started.

Anyone estimating earthworks without a factor for this will either over-order trucks or run short of fill — often both on the same job.

The three volumes

Bank volume is measured in situ. Loose volume is what comes out of the excavator, larger by the swell factor. Compacted volume is the placed fill after rolling, smaller than bank for most soils.

Swell factors commonly run from about 1.10 for dense sand to 1.30 or more for rock and clay, and they must come from testing or local experience rather than assumption.

Compaction is measured against a reference density

Compaction is specified as a percentage of maximum dry density (MDD) from a standard laboratory test, with an accompanying moisture content range. Fill placed dry will not reach density regardless of roller passes.

A specification of 95 % MDD means the placed dry density is 0.95 times the laboratory maximum for that material — a different number for every soil.

The balance

Cut and fill should be balanced on a volume basis in the same state — usually compacted fill volume against bank cut volume adjusted for the shrinkage or bulking expected.

Importing fill means trucks in, spoil removal means trucks out; getting the factor wrong turns a balanced site into a costly import exercise.

  • Measure cut in bank volume, not loose.
  • Convert fill requirements into bank volume before comparing with cut.
  • Allow for unsuitable material in the cut that cannot be used as fill.
  • Account for trench spoil separately from general cut and fill.

[F]Technical formulas

Loose volume

V(loose) = V(bank) × swell

Swell is greater than 1 for most soils.

Compacted fill from loose

V(compacted) = V(loose) / (1 + shrinkage)

Shrinkage depends on soil type and moisture.

Dry density check

ρ(dry) = ρ(bulk) / (1 + w)

w is moisture content as a decimal.

[V]Explanation of variables

SymbolMeaningUnit
swellVolume increase on excavationfactor (e.g. 1.25)
wMoisture contentdecimal
ρ(dry)Dry density achievedt/m³

[E]Worked example

Spoil from a 20 m trench

  1. 01Trench 0.6 m wide × 1.2 m deep × 20 m long = 14.4 m³ bank volume.
  2. 02Swell 1.25 for the clay encountered: 14.4 × 1.25 = 18.0 m³ loose.
  3. 03Truck capacity 8 m³ loose, so 2.25 loads — order 3 trucks.
  4. 04If 8.0 m³ of that spoil is reused as fill at a shrinkage of 10 %, it places as about 7.3 m³ compacted.

Result

A 14.4 m³ trench produces 18 m³ of spoil to cart and only about 7.3 m³ of usable fill.

[A]Practical applications

  • Estimating truck movements for a trench or basement excavation.
  • Balancing cut and fill on a building pad.
  • Planning fill import quantities.
  • Checking a compaction test result against the specification.

[!]Common mistakes

  • Comparing loose spoil volume directly with bank cut volume.
  • Ignoring moisture content when a density test fails.
  • Assuming all cut material is suitable for structural fill.
  • Forgetting that trench spoil occupies more space than the trench.

[S]References and sources

  • AS 3798 – Guidelines on earthworks for commercial and residential developmentsCompaction and testing requirements.
  • AS 1289 series – Methods of testing soils for engineering purposesDensity, moisture and compaction test methods.

Standards are cited by designation and title only — no clause text is reproduced. Purchase current editions from Standards Australia, and confirm the edition that applies to your project.